Trade Cost Distribution Site Management (12.5%)Preliminaries (10.0%)Framing & Roof Carpentry (8.2%)Masonry & Brickwork (4.7%)Plumbing & Hydraulics (4.7%)Drainage & Stormwater (3.9%)Electrical (3.9%)Other (18 trades) (34.2%)
Cost by Trade Site Management$150,090Preliminaries$120,463Framing & Roof Carpentry$98,400Masonry & Brickwork$56,710Plumbing & Hydraulics$56,040Drainage & Stormwater$47,365Electrical$46,725Other (18 trades)$411,235
EstiFlow
Preliminary Cost Estimate
Sample Duplex Project NSWAttached dual-occupancy duplex — 2 × 4-bedroom dwellings
Sample Project NSW28 April 2026
Total Contract Value (inc GST)
Priced area (m²)279.07
FSR-regulated GFA (m²)245Council / DA reporting area basis
Total ItemsTotal TradesRFI Count0.0%0.0%
2612
CHART DATA (Top 8 trades + Other — charts above update automatically)
Specialty / Joinery / Fitout215,30017.9%
Site Management150,09012.5%
Preliminaries120,46310.0%
Framing & Roof Carpentry98,4008.2%
Masonry & Brickwork56,7104.7%
Plumbing & Hydraulics56,0404.7%
Drainage & Stormwater47,3653.9%
Electrical46,7253.9%
Other (18 trades)411,235.234.2%
TOTAL1,202,328.2
TOTAL
COST SUMMARY
Net Construction Total (ex GST, ex margin)
Builder Margin
Contract Subtotal (ex GST)
GST (10%) on Contract Subtotal
Total Contract Value (inc GST)
Lockup Estimate
Fitout Balance to Completion
Rate Source: Published industry cost data (current edition)
TRADE COST BREAKDOWN
Specialty / Joinery / Fitout11215,30017.9%
Site Management5150,09012.5%
Preliminaries16120,46310.0%
Framing & Roof Carpentry798,4008.2%
Masonry & Brickwork756,7104.7%
Plumbing & Hydraulics1456,0404.7%
Drainage & Stormwater547,3653.9%
Electrical1246,7253.9%
Doors & Door Hardware745,7403.8%
Glazing & Windows1045,2403.8%
Mechanical Services / HVAC341,2003.4%
Internal Linings & Plaster338,5983.2%
Slab & Substructure532,562.62.7%
External Works & Landscape231,9502.7%
Demolition & Asbestos829,812.62.5%
Render to Masonry221,4501.8%
Roofing & Sheet Metal519,0021.6%
Painting418,8551.6%
Paving & Driveway217,4001.4%
Site Fencing116,0001.3%
Insulation312,6901.1%
Floor Finishes (timber/carpet)211,6701.0%
Waterproofing38,7500.7%
Termite Management18,0000.7%
Wet-area Tiling27,0450.6%
Excavation & Cut-to-level25,2700.4%
Site Preparation & Earthworks2
TOTAL100.0%
ESTIMATE DETAILS
Job Reference
Dwelling Count2
Project TypeAttached dual-occupancy duplex — 2 × 4-bedroom dwellings
Project TypeAttached dual-occupancy duplex — 2 × 4-bedroom dwellings
Estimate Date28 April 2026
Estimate TypeCombined Rates (Supply + Install)
Revision IDN/A
MEASUREMENT TIERS
Documented (Scheduled/Stated)Values taken from printed schedules and specifications
Derived (Measured/Computed)Quantities computed from scaled drawings and geometry
Estimated (Indicative)Estimated quantities requiring verification
ProvisionalProvisional sums and allowances
HOW TO USE THIS WORKBOOK
1. Start with this Summary sheet to review the total contract value and trade breakdown.
2. ALL dollar values on this sheet are live formulas linked to the "Bill of Quantities" sheet.
3. Open "Bill of Quantities" and edit any Rate or Quantity -- all totals on this Summary and the Trade Summary sheet will update automatically via Excel formulas.
4. Use "Program Dashboard" for the visual program overview: milestones, phase timing, critical path and procurement releases.
5. Use "Schedule Inputs" to set a project start date, edit trade lead times, and apply builder overrides.
6. Review "Indicative Program" for the dependency-aware baseline schedule and override durations where required.
7. Check "Procurement Schedule" for long-lead release dates and on-site requirements.
8. "Program Gantt" shows the printable colour-coded program with procurement, milestones, and critical path highlighting.
9. Check "Provisional Sums" for items that are allowance-based and will be subject to final measurement.
10. The "RFI Register" lists all items requiring further information or verification. Use the Status dropdown to track responses (OPEN / IN PROGRESS / CLOSED / N/A).
11. "Trade Exclusions" and "Scope Assumptions" document what is and is not included in this estimate.
12. All data sheets have filters enabled -- use the dropdown arrows in the header row to filter by trade, status, or any column.
13. Charts above are native Excel charts linked to the "Chart Data" table. When you edit rates or quantities in BOQ, the charts update automatically.
Generated by EstiFlow | 28 April 2026 | Confidential