Trade Cost Distribution Specialty Features (21.5%)Site Management (7.2%)Framing (6.6%)Concrete Slab (5.0%)Masonry (4.6%)Plastering & Linings (4.2%)Electrical Services (4.0%)Preliminaries (3.8%)Other (20 trades) (43.0%)
Cost by Trade Specialty Features$198,740Site Management$66,280Framing$61,377Concrete Slab$46,270Masonry$42,718Plastering & Linings$38,640Electrical Services$37,360Preliminaries$35,050Other (20 trades)$397,083
EstiFlow
Preliminary Cost Estimate
12 Sample Street, Sydney NSW 2000Two-storey detached dwelling · class 1a · premium specification
Sydney NSW 200010 June 2026
Total Contract Value (inc GST)$1,320,631.17
Priced GFA (m²)246.52$3,746.22
Total ItemsTotal TradesRFI CountProvisional + Allowance %Measured %
153281426.4%73.6%
CHART DATA (Top 8 trades + Other — charts above update automatically)
TradeSubtotal ($)% of Total
Specialty Features198,74021.5%
Site Management66,2807.2%
Framing61,377.46.6%
Concrete Slab46,2705.0%
Masonry42,717.54.6%
Plastering & Linings38,6404.2%
Electrical Services37,3604.0%
Preliminaries35,0503.8%
Other (20 trades)397,083.443.0%
TOTAL923,518.3
COST SUMMARY
Net Construction Total (ex GST, ex margin)$923,518.30
Builder Margin$277,055.49
Contract Subtotal (ex GST)$1,200,573.79
GST (10%) on Contract Subtotal$120,057.38
Total Contract Value (inc GST)$1,320,631.17
Lockup Estimate (Stage 1)$392,894.90
Fitout Balance to Completion$530,623.40
Rate Source: Published industry cost data (current edition)
TRADE COST BREAKDOWN
TradeItemsSubtotal ($)% of Total
Specialty Features15198,74021.5%
Site Management466,2807.2%
Framing861,377.46.6%
Concrete Slab746,2705.0%
Masonry842,717.54.6%
Plastering & Linings338,6404.2%
Electrical Services1537,3604.0%
Preliminaries935,0503.8%
Plumbing & Drainage1134,6003.7%
Mechanical Services734,3003.7%
Glazing & Screens1732,9103.6%
External Finishes330,0003.2%
Doors & Frames828,7683.1%
STRUCT228,5003.1%
Floor Coverings328,3503.1%
Roofing527,4903.0%
Painting527,3103.0%
Render226,6502.9%
Insulation319,8422.1%
Civil Infrastructure114,0001.5%
Tiling212,8401.4%
STAT511,9071.3%
Stormwater Drainage39,8651.1%
Waterproofing38,341.40.9%
SERV18,0000.9%
COMPLY18,0000.9%
Termite Protection14,5000.5%
Site Preparation & Earthworks1$9100.1%
TOTAL131$923,518.30100.0%
ESTIMATE DETAILS
Job Reference
Dwelling Count1
Project TypeTwo-storey detached dwelling · class 1a · premium specification
Storeys2
Estimate Date10 June 2026
Estimate TypeCombined Rates (Supply + Install)
Revision IDN/A
MEASUREMENT BASIS
Measured128Quantities taken from drawings, schedules or computed geometry.
Provisional23Scope included with final quantity, rate or product selection still to be confirmed.
Allowance2Authority, statutory, insurance or selection allowances carried for budget completeness.
HOW TO USE THIS WORKBOOK
1. Start with this Summary sheet to review the total contract value and trade breakdown.
2. ALL dollar values on this sheet are live formulas linked to the "Bill of Quantities" sheet.
3. Open "Bill of Quantities" and edit any Rate or Quantity -- all totals on this Summary and the Trade Summary sheet will update automatically via Excel formulas.
4. Use "Program Dashboard" for the visual program overview: milestones, phase timing, critical path and procurement releases.
5. Use "Schedule Inputs" to set a project start date, edit trade lead times, and apply builder overrides.
6. Review "Indicative Program" for the dependency-aware baseline schedule and override durations where required.
7. Check "Procurement Schedule" for long-lead release dates and on-site requirements.
8. "Program Gantt" shows the printable colour-coded program with procurement, milestones, and critical path highlighting.
9. Check "Provisional Sums" for items that are allowance-based and will be subject to final measurement.
10. The "RFI Register" lists all items requiring further information or verification. Use the Status dropdown to track responses (OPEN / IN PROGRESS / CLOSED / N/A).
11. "Trade Exclusions" and "Scope Assumptions" document what is and is not included in this estimate.
12. All data sheets have filters enabled -- use the dropdown arrows in the header row to filter by trade, status, or any column.
13. Charts above are native Excel charts linked to the "Chart Data" table. When you edit rates or quantities in BOQ, the charts update automatically.
Generated by EstiFlow | 2 July 2026 | Confidential