How to scope owner supplied appliances in a building tender
If the owner buys the dishwasher, exclude its purchase price from the builder’s tender. Keep the work the builder has agreed to arrange. An integrated dishwasher can need a matching cabinet panel, a handle, fitting and final connections. The words “dishwasher by owner” leave all of that open.
The decisions behind the dishwasher line
| When | Who acts in this example | What they record |
|---|---|---|
| The joiner prepares the cabinet drawings | Owner | Give the builder the exact product code and the manufacturer’s current installation sheet. |
| The joiner cuts the panel | Joiner | Match the sheet to the cabinet opening, panel and handle. Mark the agreed detail on the kitchen drawing. |
| The owner books delivery | Builder and owner | Agree on the date, the person receiving the carton and a dry place to store it. Check whether delivery reaches that spot. |
| The carton arrives | Person receiving it | Check the product code against the selection. Record visible damage or a missing carton and tell the owner who placed the order. |
| The kitchen is ready for fitting | Builder | Confirm the appliance, panel, handle and required fittings are on site. Arrange the named trades and check the door clears the plinth when it opens. |
A dishwasher line you can put in a tender
Here is example wording for a kitchen where the owner wants a panel to match the cabinet doors.
“The owner will buy the integrated dishwasher and arrange delivery to site on the date agreed with the builder. The builder’s price includes the matching cabinet panel and handle, fitting the appliance and panel, and the final water, waste and power connections by the builder’s licensed trades. The builder pays the plumber and electrician for that connection labour. The dishwasher purchase and the retailer’s delivery charge are outside the builder’s price.”
Use that line only when the trades have priced the named work. If the retailer will install the appliance, get the installation inclusions in writing. Check whether the retailer fits the cabinet panel and handle. Keep a price against whoever will finish that work.
Put the actual dates and trade names beside the tasks in the job copy. A joiner may need the installation sheet weeks before the builder needs the appliance on site. Give the owner both dates.
If the owner changes the selection
Suppose the owner sends a different product code after approving the kitchen drawing. Send the new installation sheet to the joiner before they cut. Ask them to check the panel size, fixing detail and door clearance. Have the trades confirm the service locations too.
Record what can stay, what needs to be changed and any price or delivery change. Give the owner that difference while they can still choose which appliance to buy. Update the schedule and drawing together so the receiver on site checks the carton against the latest selection.
EstiFlow’s scope of works service
Questions builders ask
What if the builder already allowed for the appliance?
Trace the allowance to the tender line. If it covered supply only, remove that supply amount when the owner takes over the purchase. If a kitchen quote bundled supply and fitting, ask for a split first. Identify the panel and connection costs that still belong in the tender.
Where should the schedule go?
Give the owner a copy with the tender. Put the relevant rows in the joinery, plumbing and electrical packages. Each trade can see what it needs to price and which drawing goes with it.
Sources
- EstiFlow scope of works service (accessed 22 November 2026)
- How to prepare trade packages for pricing (accessed 22 November 2026)
- How allowances for fittings and their installation work (accessed 22 November 2026)
Related guides
- How to prepare trade packages for subcontractor pricing
- Provisional sums and prime cost items in a builder’s tender
Pavlo Hanna, EstiFlow