Construction scope of works template for builders

A scope of works tells each trade what to supply, what to install and where its responsibility ends. Issue it with the drawing revision and the bill of quantities so each subcontractor prices the same work.

Write the handover between trades

Illustrative scope for three internal swing doors. The door schedule gives the count, but a price for “three doors” leaves the hardware, finishing and handover open.

Supply
The builder supplies three door leaves and three passage sets. Deliver them to the openings before the carpenter starts.
Install
The carpenter fits three leaves to existing frames, installs the passage sets and checks that each door swings and latches. Allow three hinges per leaf, nine hinges in total, supplied and fitted by the carpenter.
Paint and hand over
The painter prices the finish to the leaves and frames. The carpenter and painter agree when to remove and refit handles so the task appears in one price.
Clarify before award
Confirm the handing of the third door on the schedule. Each tenderer records the assumption used. The builder issues the answer to everyone who received the package.

In this example the buyer can compare labour to hang three doors and the supply and installation of nine hinges. A return that also charges for the leaves needs clarification before award. Replace these assumptions with the issued door and hardware schedules.

Use the template to compare tenders

  1. Before you send it

    Replace the illustrative entries. Give each row an item ID, a trade and a drawing revision. Enter the measured quantity, the supply and installation duties, any exclusions and who receives the finished work.

  2. When prices come back

    Keep one copy per tenderer. Ask them to mark each row included, excluded or qualified and write any condition beside it. A blank response needs an answer before you compare totals.

  3. When you let the package

    Record the answer against the original row. Send the same revision to affected trades, collect their acknowledgements and attach the agreed scope and exclusions to the order.

The public commercial procurement workbook shows how a delivered package is organised. Open Package Index and then Doors, Frames & Hardware. The public viewer masks prices. The three door example above was written for this template. Inspect the sample trade packages.

What does the tender scope cost?

Which EstiFlow estimates include a scope of works?
The full Fitout, Commercial and Large commercial estimate tiers include a scope for each trade package. A residential customer can add a tender scope to a full residential estimate for A$99 inc GST.
Does a Trade Estimate Pack include a tender scope of works?
A tender Scope of Works comes with the full commercial estimate tiers. It is not part of a Trade Estimate Pack, and it can be added after delivery.
Check Trade Estimate Pack inclusions

Full commercial estimate fees

Per estimate, including GST and the tender scope.

Commercial Fitout
A$1,099
Small to mid commercial
A$1,490
Commercial Large
A$1,990

Commercial estimates are typically delivered within 2 business days from payment and a complete document set. Major-project timing is agreed with your quote.

Check the published catalogue and residential add-ons

Check which commercial tier fits

Match the scope to the measured bill of quantities

Pavlo Hanna, EstiFlow

Get your estimate