Knockdown rebuild costs from demolition to the new house
A knockdown rebuild proposal needs to say how the demolition contractor will leave the block and how the new builder expects to receive it. Agree those two descriptions before adding the prices. A cleared block can still contain old footings, paving or disconnected services.
Define the condition of the block at handover
On the survey, mark the house and outbuildings to remove, the trees and fences to keep, and the access the next trade will need. List slab removal, buried footings, disposal and filling of voids separately. Record the agreed handover levels against the survey.
Give each tenderer the same available site reports and service information. Identify who arranges disconnections and who provides temporary services for the new build. If an old footing has no recorded depth, ask how extra removal would be measured and agreed.
Illustrative measurement of an existing driveway
Suppose an existing concrete driveway is 18 m long and 3 m wide. The first 6 m from the street will stay as access. Mark 18 m² to protect and the remaining 36 m² to remove. State the assumed slab thickness if the demolition price depends on it.
If the retained section must come out after deliveries finish, add a separate 18 m² removal item for that visit. Give the new concreter the proposed driveway outline. Its area may differ from the 54 m² of old paving.
Compare the replacement house with like work
EstiFlow’s September 2026 residential study gives a median of A$4,013 per m² across 40 estimates classified as single dwellings. It uses recorded gross floor area and excludes the builder’s margin and GST. The study groups several kinds of work together and gives no separate knockdown rebuild rate.
For your proposal, carry forward the agreed demolition price. Check the new builder’s site allowance against the handover levels and the soil report. Show any remaining excavation or fill under the new build so the owner can see where one contractor finishes and the next begins.
Questions about this estimate
What does an estimate for one replacement house cost?
EstiFlow’s Standard Residential estimate fee is A$499 including GST for one house. Send the removal plan with the new house drawings and identify any demolition arranged directly by the owner.
Where can I see how the estimate is set out?
EstiFlow’s public residential sample shows how the cost report and trade workbook organise the work. Detailed prices are withheld in the viewer. Use the sample to check the format and your own plans to establish quantities.