Townhouse estimating by unit type and common works
Start a townhouse proposal with a list of unit numbers and the plan type for each. Then mark the work outside the units. A layout change to one townhouse can affect its courtyard and garage while leaving the common road and stormwater system untouched.
Count the copies of each plan
List each townhouse against its floor plan, finish schedule and garage type. Check the end units against the street elevations. Put changes in a column beside the unit number so the supplier can see which kitchens or windows repeat exactly.
On the civil plan, mark where each private driveway meets the common road. Give the paving trade both outlines. Check the drainage pits and grates against the drainage contractor’s inclusions before combining the trade prices.
Illustrative measurement of six courtyards
Suppose four units each have a 3 m by 4 m paved courtyard. The two end units each have a 4 m by 5 m paved courtyard. The four smaller areas total 48 m² and the two larger ones total 40 m². Carry 88 m² of private paving.
If the same plan shows a separate common path 20 m long and 1.5 m wide, record another 30 m² under common works. A change to the courtyard finish then affects 88 m². The path can keep its original finish and price.
Compare the offers for common works
Ask for separate amounts for the common road, drainage, landscaping and lighting. A rate for courtyard paving may assume a different base from the vehicle pavement. Issue the relevant section with each enquiry and name the trade that prepares the base.
If owners will move in before the last units are finished, mark the areas they need to reach. Ask the builder to identify temporary access, barriers and any return visits that follow from the handover dates.
Questions about this estimate
What are the townhouse estimate fees?
EstiFlow charges A$899 for a townhouse development of up to 4 units, A$1,099 for 5 to 8 units and A$1,599 for 9 to 15 units. Each fee covers one development and includes GST.
Can I use the published small townhouse observations to price a whole development?
EstiFlow’s September 2026 residential study lists only two small townhouse observations. It gives no townhouse median. For a larger development, price the plan types and count the copies, then add the common works measured from the civil and landscape drawings.