Concreting takeoff for slabs, beams and slab edges
A concreting takeoff starts with cubic metres for each pour. The same slab can also have square metres of finished surface and metres of joints. EstiFlow lists concreting as Concrete.
Read the slab plan alongside the sections
Trace each slab thickness on the structural plan. Use the section to locate steps, rebates and beams. Deduct documented voids from the slab area and record their dimensions. Keep pads and footings separate where their depth or concrete specification differs.
Measure the area receiving each surface finish. Trace saw cuts and construction joints in metres by detail. For formed faces, record the length and the height in contact with concrete. An edge cast against ground has a different scope from an edge with a shutter.
Illustrative takeoff for a slab with a deeper beam
Assume an 8 m by 5 m slab with no openings. The slab is 125 mm thick. Convert the thickness using 1,000 mm per metre. The slab covers 40 m² and contains 40 × 0.125 = 5 m³ of concrete.
One beam inside that footprint runs 8 m, is 300 mm wide and measures 450 mm from slab top to beam bottom. The slab already includes the upper 125 mm. The extra depth is 325 mm, so add 8 × 0.30 × 0.325 = 0.78 m³. The net pour is 5.78 m³. The top finish still covers 40 m².
Agree who forms and reinforces the pour
The catalogue lists Reinforcement and formwork separately. Mark who supplies and fixes the steel, who forms the edges and who places and finishes the concrete. Ask who provides the pump and prepares the subgrade. Record any order allowance separately from the net pour.
Questions about this estimate
What if the beam depth is measured below the slab?
Use that depth directly for the additional beam volume. Deduct the slab thickness only when the dimension includes it. Keep the section reference beside the calculation.
How do I measure a setdown in a wet area?
Read both the top and underside levels. A lower top with a matching drop in the underside can keep the same slab thickness. Split out the area if the section shows a change in thickness.