HVAC takeoff for duct runs, fittings and equipment
An HVAC takeoff follows each air path from a tagged unit to its outlets. Measure straight ducts by size and count the components between them. EstiFlow lists this trade as Mechanical and HVAC.
Trace one duct system at a time
Keep supply, return and exhaust runs separate. Mark changes of width, depth or diameter. Measure straight sections between fitting faces, including vertical runs shown in section. Count bends, branches, transitions and dampers by size. List flexible connections by length and diameter.
Match each unit tag on the plan to the equipment schedule. Count grilles and diffusers by tag and size. Where an outlet includes a plenum box, check whether the box comes with the outlet or needs its own line.
Illustrative takeoff for insulation on straight duct
Assume the main is 8 m long with outside dimensions of 0.6 m by 0.3 m. Insulation covers its four long faces. The perimeter is 2 × (0.6 + 0.3) = 1.8 m, giving 1.8 m² of duct surface per metre of run. The main contributes 8 × 1.8 = 14.4 m².
Two branches each have 3 m of straight duct, 0.4 m wide and 0.2 m deep. Their perimeter is 1.2 m, so they add 2 × 3 × 1.2 = 7.2 m². Record 21.6 m² of straight duct surface to insulate. Fitting covers, seams and overlaps need separate quantities before ordering insulation.
Mark the connections that cross trade boundaries
At each unit, identify who provides power, the isolator and control wiring. Trace the condensate drain to its agreed connection with plumbing. Mark ceiling access panels beside the items they serve and identify who supplies and fits them. List testing and balancing where the specification calls for them.
Questions about this estimate
What if a plan shows outlets but gives no duct sizes?
Count the tagged outlets and mark the routes shown. Ask for the duct sizes and sections before measuring sheet or insulation area. Keep equipment capacity as an open item if the schedule also omits it.
Does a damper on the plan and in the schedule count twice?
Match the damper tag and location across both documents. Count one physical damper and record its size, actuator and access requirements. Flag unmatched tags for clarification.