Painting takeoff for walls, ceilings, doors and trim
A painting takeoff records the surface area once and lists the coats that surface receives. Keep new plaster, previously painted walls and timber trim on separate lines so the painter can allow for their preparation. Painting appears in the EstiFlow selector.
Measure what the painter will touch
Use the room perimeter and paint height for the walls. Deduct openings and any areas taken by tiles or exposed finishes. Measure the ceiling to its actual shape. List bulkhead sides and undersides where the ceiling steps.
Count door leaves by size, finish and number of painted faces. Measure skirtings and architraves in metres by profile. Identify frames, reveals and exposed door edges separately. Mark the surfaces that need patching or sanding before their first coat.
Illustrative takeoff for two wall coats
Assume a 4 m by 3 m room with walls 2.5 m high. Its perimeter is 14 m, giving 14 × 2.5 = 35 m² of gross wall face. One door opening measures 0.9 m by 2 m and one window opening measures 1.6 m by 1.25 m. Deduct 1.8 m² and 2 m² to leave 31.2 m².
For two specified finish coats, record 31.2 m² per coat. The painter covers 2 × 31.2 = 62.4 m² across both applications. A sealer, if specified, gets its own line. The flat ceiling is another 4 × 3 = 12 m² under its own finish.
Agree on patching and factory finishes
Identify who finishes the plasterboard joints and who prepares that surface for paint. Mark the joinery and metalwork supplied with a factory finish. Where site touch ups are specified, list the affected items and assign that work to one trade.
Questions about this estimate
How do I compare two painting quantities for the same room?
Ask for the net area, preparation, sealer and number of finish coats on each line. One painter may have listed the area once with both coats included. The other may have shown the area of each application.
Does the window deduction include painted reveals?
Deduct the opening from the flat wall face. Measure the painted heads, jambs and sill from their own lengths and depths. Check the finish schedule for which of those faces receive paint.